Ain Tsila is located within the Isarene permit in Blocks 228 and 229a, in the Illizi basin.
The produced gas from the field will be exported via pipeline to the main Algerian gas transmission system at the Tin Fouye Tabankort (TFT) field, located around 100km from Ain Tsila.
First production from Ain Tsila is expected in 2017.

Ain Tsila Gas Condensate Field

Ain Tsila is a gas condensate field located in the Illizi basin, Algeria. It is situated within the Isarene permit in Blocks 228 and 229a.

The project is owned by Groupement Isarene, a joint venture of Petroceltic, Sonartech and Enel Trade SPA. Petroceltic holds 56.625% working interest in the project, while Sonatrach holds a 25% share and Enel holds the remaining 18.375% interest.

The Plan of Development for the Algerian offshore field was submitted in January 2012 and was approved in December the same year. The project was declared commercial in August 2012.

The front end engineering and design (FEED) phase of the project commenced in 2014. The field is expected to start initial gas production in 2020.

“The gas condensate field was discovered in 2009.”

Discovery, geology and reserves of the Algerian gas condensate field

The Ain Tsila field is estimated to hold reserves of 2.1 trillion cubic feet of sales gas, 67 million barrels of condensate and 108 million barrels of liquid petroleum gas (LPG).

The gas condensate field was discovered in 2009, following the drilling of the Ain Tsila-1 well. The well was the ninth-largest discovery worldwide that year. The field covers an area of over 1,000km2.

Hydrocarbons in the Illizi Basin are located within Silurian shales found in Carboniferous, Devonian and Ordovician reservoirs, with the largest volumes found in the Ordovician reservoirs.

The Isarene concession, in which the gas condensate field is located, covers an area of around 2,564.8km2. It comprises three other prospects, namely Isarene Nord-Est, Isarene Nord-Ouest and Hassi Tab Tab. The Amenas project is located east of the permit and the Tin Fouye Tabankort field is north of the permit.

Ain Tsila field development and infrastructure

“The field is expected to start initial gas production in 2020.”

The gas condensate field is expected to be developed over a period of 30 years, during which 124 wells will be drilled. The field will initially start production from 18 vertical wells.

Gas will be produced via a new gas-processing plant at an annual average plateau rate of 355 million standard cubic feet per day. Production is expected to remain stable for 14 years.

The new gas-processing plant will incorporate water separation, condensate and LPG recovery equipment, gas compression, export pumps and metering facilities.

The produced gas will be exported via a 100km-long pipeline to the main Algerian gas transmission system at the Tin Fouye Tabankort (TFT) field. Sonatrach will market gas products from the field.

Up to six appraisal wells were drilled prior to the submission of the drafts for the Declaration of Commerciality and Plan of Development for the project. The vertical and horizontal wells were drilled using KCA-Deutag-Nomad-class Rigs T-211, T-212 and the 2,000 hp Dalma Rig LR-12.

AT-4, AT-6, AT-8 and AT-7 are vertical wells, while AT-5Z and AT-9 are horizontal wells.

The drilling works commenced in 2010 and the testing of the six appraisal wells was carried out from January to December 2011. The drilling and testing works were carried out using data-driven 3D seismic techniques.

The Nomad-class drilling rigs are capable of drilling wells to 15,000ft or more. They incorporate special health, safety and environment (HSE) features, such as pipe-handling equipment, a derrick anti-collision system, iron roughneck, a man-riding winch, dedicated equipment maintenance platforms, and special noise insulation in the generator packages.

Contractors involved

The FEED contract was awarded to Chicago Bridge and Iron, an engineering and construction company based in the US, in September 2014.

Sinopec International Petroleum Service was awarded the drilling rig contract by Groupement Isarene, a consortium of Sonatrach, Petroceltic and Enel, in April 2015.

The engineering, procurement, and constrcution (EPC) contract worth $1bn was awarded to Petrofac. Petrofac is responsible for performing the commissioning, start-up and performance testing of the field for 42 months.

 

NRI Energy Technology


Related content


Shtokman Gas Condensate Deposit, Russian Federation

The Shtokman gas condensate deposit lies in the Barents Sea, north Russia.

Oudna Field, Tunisia

The Oudna oil field is located in the Gulf of Hammamet, 80km off the northern eastern coast of Tunisia.