Oman’s national energy holding company OQ has awarded a package known as ‘Station C’, which is part of the Bisat early oil production facility project, to US oil and gas contractor Exterran Corporation.

The contract is estimated to be worth about $80m, and workers have already been mobilised, according to information first obtained by regional projects tracker MEED Projects.

The four-year contract has the option to be extended for one additional year. Construction is expected to be completed within 21 months.

The contract will use the design-build-own-operate-maintain (DBOOM) model.

The contract was originally tendered in May 2020, but the tender process saw significant delays.

Apart from Exterran, companies that bid for the project were:

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.
  • Alkhorayef Group (Saudi Arabia)
  • Enerflex (Canada)
  • Oman Holdings International Company (local)
  • Schlumberger (US)
  • Towell Engineering (Oman)

Contractors submitted expressions of interest (EoI) for the package on 12 March 2020.

The project aims to process and treat a minimum of 330,000 barrels a day (b/d) of gross reservoir fluids.

This will be made up of 300,000 b/d of produced water treatment capacity and 30,000 b/d of crude oil processing capacity.

The project also includes the treatment of produced water to required disposal specifications and pumping of produced water to designated disposal water wells at the required injection pressure after treatment.

The Bisat early production facility project includes plans for three separate stations.

The other two are known as Station A and Station B.

The contract for Station A was awarded to Schlumberger in January 2019 and was completed earlier this year.

The contract for Station B was also awarded to Schlumberger in 2020 and execution is currently under way.


Energy Transition in the Middle East    

A major new report from MEED looks at how the global shift away from fossil fuels is reshaping energy policy in the Middle East and North Africa, and its impact on business and project investment. 

Learn more about the report here


This article is published by MEED, the world’s leading source of business intelligence about the Middle East. MEED provides exclusive news, data and analysis on the Middle East every day. For access to MEED’s Middle East business intelligence, subscribe here.