Kuwait-based contractor Spetco and China’s Jereh have been awarded main contracts to build Kuwait Oil Company’s (KOC) Jurassic production facilities (JPF).
The projects are known as JPF-4 and JPF-5. The contract for JPF-5 was worth RMB2.7bn ($426m), making it the biggest oil and gas contract Jereh has won since it was established in 1999, according to a statement released by the company.
In its statement, Jereh said that it started the prequalification for the project in early 2018 and ‘organised clarification exchanges with KOC’ more than a hundred times as part of the tendering process.
It added: “In the bidding stage, after two rounds of quotations, Jereh Oil & Gas Engineering finally stood out from the fierce competition of the five companies participating in the bidding and successfully won the bid at a non-lowest price.”
The JPF-5 project has been divided into two phases, according to Jereh.
These include a 26-month engineering, procurement, construction and commissioning period and a 60-month operation and maintenance service period.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataLi Weibin, vice-president of Jereh, said: “This cooperation with KOC is the first breakthrough of Jereh’s integrated surface engineering solution for oil and gas fields in the Kuwait market.
“It is another great feat of Jereh’s internationalisation strategy in the Middle East. KOC is a leading international high-end oil company.
“The implementation of this project will effectively enhance Jereh’s brand influence in Kuwait and the entire Middle East and North Africa market, laying a solid foundation for the company to further expand”.
In October, MEED revealed that Spetco and Jereh had submitted the two lowest bids in the second round of bidding for JPF-4 and JPF-5.
Spetco submitted a low bid of $398.2m for JPF-4, and Jereh submitted a low bid of $426m for JPF-5 with its local partner Napco.
Bids were submitted by four companies on 6 October, according to industry sources.
The full list of bidders was:
- Spetco (Kuwait)
JPF-4: $398,180,000
JPF-5: $428,212,500 - NBTC (Kuwait)
JPF-4: $446,821,409
JPF-5: $448,321,409 - Jereh (China) with Napco (Kuwait)
JPF-4: $429,000,000
JPF-5: $426,000,000 - Al-Khorayef Group (Saudi Arabia)
JPF-4: $449,463,000
JPF-5: $449,463,000
The Kuwaiti contractor Gofesco, which participated in the first round of bidding, did not get a bid bond and did not submit a bid in the second round.
The facility known as JPF-4 is due to be located close to the Sabriyah field in the north of Kuwait. JPF-5 will be less than 10km to the east of JPF-4.
Both facilities will conduct testing, processing, treating and handling of wet and sour hydrocarbon well fluids from several oil and gas fields.
These include Raudhatain, Sabriyah, Northwest Raudhatain, Umm-Niqa, Dhabi, Bahra and the fields of Marrat and Najmah-Sarjelu and other formations in the Jurassic fields.
Both projects are onshore surface production facilities and will be implemented on a build-own-operate (BOO) basis by a contractor, with an option for KOC to buy them back at a future date.
The facilities are due to be built with the capacity to produce 50,000 barrels a day (b/d) of treated sweet crude (Jurassic light oil with 40°- 50° American Petroleum Institute (API) gravity) and 150 million standard cubic feet (MMscf) a day of sweet and dehydrated rich gas.
They will include a produced-water treatment unit, a sulphur recovery unit and associated utilities and supporting systems.
Bidders have been told that the execution stage of services for each facility will total 780 calendar days.
This includes 720 days for the design and engineering, project management, supply and procurement, construction, testing and mechanical completion of each facility.
Under the terms of the contracts, commissioning, stabilisation and successful performance testing of the facility should be completed within 60 calendar days of the mechanical completion of the facility.
The winners of the contracts will then operate and maintain the facilities for five years.
Energy Transition in the Middle East
A major new report from MEED looks at how the global shift away from fossil fuels is reshaping energy policy in the Middle East and North Africa, and its impact on business and project investment.
Learn more about the report here.