Tyrihans is located on the Halten Bank in the Norwegian Sea, 35km south-east of the Kristin field in roughly 285m of water.
An electrically heated pipeline links Tyrihans with the Kristin platform.
Condensate and crude is combined with Kristin output after stabilisation and piped to the Åsgard C storage ship.
Tyrihans is developed by a total of 12 wells connected to five subsea templates.
Plateau production for gas is expected to be about 13 million m³/d, while plateau production for liquid is expected to be 13,000m³/d.

Recoverable reserves are put at roughly 186 million barrels of oil and condensate

Tyrihans is located in the Halten Bank area of the Norwegian Sea, 35km south-east of the Kristin field, in roughly 285m of water.

The discovery is comprised of two structures – Tyrihans North, a gas and condensate discovery, and Tyrihans South, an oil discovery. Part of the Tyrihans South field extends into production licence 091, while Tyrihans North lies exclusively within production licence 073.

Drilling in the Tyrihans field began in April 2008 and it was not until 8 July 2009 that the production had commenced. The production at the field is expected to last until 2029. The field was officially opened in March 2011.

Recoverable reserves are put at roughly 186 million barrels of oil and condensate, and 41.5 million cubic metres of rich gas. Statoil has a 58.84% interest. Its partners are Total E&P Norge with 23.18%, Eni Norge with 6.23% and Mobil Development Norway with 11.75%.

Exporting the rich gas and liquid

“The production at the field is expected to last until 2029. The field was officially opened in March 2011.”

In July 2005, Statoil submitted a PDO (Plan for Development and Operation) for Tyrihans and began procurement. A 43km pipeline carries the wellstream to the Kristin platform for separation.

The rich gas from both fields, Tyrihans and Kristin, is then exported via the Åsgard Transport system which runs to Kårstø, north of Stavanger. There, the gas is processed before its onward transmission to European customers.

Meanwhile, the liquids production – condensate and crude – is combined with Kristin output after stabilisation and piped to the Åsgard C storage ship for export by shuttle tanker.

Tyrihans Nor discovery well details

In 1984, the Tyrihans Nor discovery well 6407/1-3 found hydrocarbons at 3,600m in the middle Jurassic sandstones. It was drilled by the Dyvi Delta. A gas cap extended to 3,687.5m followed by an oil zone down to 3,709m. The Dyvi Delta had previously drilled the Tyrihans Sor wildcat well 6407/1-2.

The Tyrihans Nor well was followed by the 6407/1-4 appraisal, drilled by the Byford Dolphin in 1996 to 3,805m, while in 2002 a Tyrihans Sor appraisal was drilled by the Stena Don.

Development of the Norwegian field

Tyrihans has been developed with a total of 12 wells, some multilateral, breaking down to nine for production, two for gas injection and one for the injection of unprocessed seawater. The wells also include the use of smart well technology for improved recovery from subsea-completed fields.

All the wells are connected to five subsea templates. Statoil had entered a three-year, NOK2bn agreement to use the Transocean Arctic semisubmersible for drilling and completion. Subsea pumps are used for injection of seawater, while gas is injected from the Åsgard field.

Subsea system and Åsgard B pipeline

The seabed installations on the field were carried out in 2007. All the 12 wells are held with the help of four production frames, which are in turn connected to the Kristin pipeline. Gas supply for gas injection and gas lift in the production wells is compensated from the Åsgard B pipeline.

The planning of gas injection has been done to last until 2015. Injection of sea water for pressure support is done through a subsea facility.

An electrically heated pipeline links Tyrihans with the Kristin platform. Tyrihans connects to Kristin through a 43km, 16in pipeline, whereas Tyrihans connects to Åsgard B through a 10in pipeline. The pipeline was laid in 2007.

The pipeline for the wellstream is made of special steel. It consists of an outer carbon pipe and an inner stainless steel pipe. This is the first time that Statoil has installed such a pipeline.

Production from Statoil’s field

The Åsgard B platform required modification, as did Kristin, although some modifications were made while the platform was under construction. A 250t processing module was built and installed on the platform in 2008.

Plateau production is expected to be about 96,000 barrels of oil equivalent per day (boepd) by 2016-17, while Statoil’s share is expected to be 56,000boepd.

Contracts awarded for the Tyrihans field development

Statoil awarded a NOK300m contract to Butting of Germany for the delivery of steel pipe for the pipeline linking Tyrihans with the Kristin platform. The pipeline was successfully delivered in December 2006. Ramboell Denmark conducted the engineering for the pipelines and their routes.

“The rich gas from both fields, Tyrihans and Kristin, is then exported via the Åsgard Transport system which runs to Kårstø.”

Stolt Offshore (Acergy) was awarded with a NOK550m contract to lay two pipelines from Tyrihans to Kristin.

Statoil awarded FMC Kongsberg with a $225.4m contract for the subsea systems. This covered assistance and maintenance of the facility during installation and operation.

In May 2012, Statoil was provided consent by the Petroleum Safety Authority Norway to deploy the Transocean Searcher semisub for re-completion of 6407/1A-4-H well. The well is located in production license 091 and is expected to be re-completed by March 2013.

Statoil was also granted approval for using Transocean Leader semi-submersible drilling vessel in November 2012 for deployment on the Tyrihans field. The vessel will be used for drilling of production wells in the 091 license. The work is expected to start in December 2012.

In November 2012, FMC Technologies won an order worth about $39m to deliver a pair of subsea trees and three choke modules in 2013.

Wire line tractor services for Tyrihans and Statoil’s other fields in the Norwegian Continental Shelf will be provided by Aker Well Services as part of a $65m contract awarded in October 2012.


Related content


Valemon Field, Norwegian Sea, Norway

The Valemon field is located between production licence 050 and 193 in the Norwegian Sea.

Åsgard, Norwegian Sea, Norway

The Åsgard oilfield lies on the Haltenbank in the Norwegian Sea, 200km offshore Norway and 50km south of Statoil’s Heidrun field.